allinmw.com / Guides / Data center megawatts explained
Guide · Definition

Data center megawatts explained: MVA, facility MW, IT MW and installed MW

"A 60 MW data center" can mean the grid connection, the total site load, the power available to servers or the generators on site. The numbers differ by a factor of two or more. This guide defines each one, shows how they connect and explains how redundancy inflates installed capacity.

Updated October 20267 min readBy Ziya DemirData center project directorFounder of allindatacenter.com

In short

  • MVA is the grid connection; facility MW is the site load; IT MW is what servers get and tenants lease.
  • MVA × power factor − headroom = facility MW; facility MW ÷ peak PUE = IT MW.
  • A 60 MVA connection typically yields about 38 MW of IT, 63 % of the nameplate.
  • Installed MW includes redundancy: N+1 (4+1) is 1.25 × load, DR 1.33 ×, 2N 2.00 ×.
Chain

The power chain, from grid to rack

Power arrives from the utility at high voltage, is stepped down by transformers, distributed by switchgear, protected by UPS and delivered to racks by busbar or cable. At each step some capacity is reserved or lost, so the number shrinks from the grid to the rack. The calculator on the home page walks the same chain.

Terms

Six numbers, six meanings

TermMeaningUsed for
MVAApparent power the utility will supplyThe ceiling for everything below
Facility MWEverything the site draws at peak: IT, cooling, losses, officesSizing generators and the substation
IT MW (critical load)Power available to servers, storage and networkWhat tenants lease and investors value
kW per rackDesign power per cabinetCooling type, floor loading, busbar sizing
MWh per yearEnergy actually consumedBills, PUE reporting, carbon
Installed MWUPS and generator nameplate including redundancyEquipment cost; always above the load
Step 1

MVA vs MW: power factor and headroom

The grid contract is in MVA, apparent power. Real power in MW is MVA × power factor; modern IT with active power-factor correction runs close to 0.95 or better. Operators also keep headroom, often around 10 %, for start-up currents, growth and the utility's limits. 60 MVA × 0.95 = 57 MW; minus 10 % headroom = 51.3 MW of facility power.

Step 2

Facility MW vs IT MW: the peak PUE

Facility power includes cooling and electrical losses. Dividing by the peak design PUE, not the annual average, gives the IT capacity that can be guaranteed on the hottest day: 51.3 MW ÷ 1.35 = 38.0 MW IT. The annual PUE, usually lower, is used for energy. More on PUE at allinPUE.

Redundancy

Installed MW and redundancy

TopologyMeaningInstalled ÷ load
NExactly the capacity needed, no spare1.00
N+1 (4+1)One spare module per block of four1.25
DR (4 make 3)Distributed redundant: four systems carry three loads1.33
2NTwo complete, independent paths2.00

UPS capacity is sized on the IT load; generators on the facility load. For 38 MW IT with N+1: about 47.5 MW of UPS and 64 MW of generators.

See your own chainEnter MVA, power factor, headroom, PUE and density; get IT MW, racks and installed plant.
Open the calculator →
Practice

Five questions to ask about any "MW"

  1. Is this MVA, facility MW or IT MW?
  2. Is it contracted grid capacity or the site's design load?
  3. Which PUE was used, peak or annual?
  4. Is it built, under construction or planned?
  5. Does it include redundant plant?
Questions

Questions about megawatts

What does "a 100 MW data center" usually mean?

Most often 100 MW of IT, the leasable critical load. Utilities and planners often mean grid capacity instead, which is larger. Always ask.

Why is IT MW so much lower than MVA?

Power factor, headroom and the cooling and losses counted in PUE each take a share. Together they often leave 60–65 % of the nameplate for IT.

What is critical load?

The IT load that must stay up through any failure: servers, storage and network. It is protected by UPS and generators.

Does 2N double the cost?

It roughly doubles the UPS and generator plant, not the whole facility. Shell, cooling and fit-out grow far less.

Sources

Sources

  • Definitions follow common industry usage; redundancy factors as shown in the home page terms section.
  • Worked figures use the calculator defaults: 60 MVA, PF 0.95, 10 % headroom, peak PUE 1.35.
Next

Keep reading